1

Consultancy Services for owner Engineering for Construction of Bibiyana- III 400MW Combined Cycle  Power Plant  Under Bangladesh Power Development Board (BPDB). Funded by JICA project cost Tk 3500.crore

Design, construction supervision, of steam turbine gas turbine, Boiler House, Water cooler House, WAREHOUSE WORK Shop (still Frame ) & Rcc, Structure Plant Rcc House) jetty face Building staff quarter, Internal Road, Water Treatment Land Development etc.

 

August 2008 to

December 2012

 

176.39 Lakh

JV of Minconsult, Malaysia

2

Consultancy Services for owner Engineering for Construction of  150 MW Peaking Power Plant Complex at Siragonj, Funded by Asian Development Bank (ADB) Under Bangladesh Power Development Board (BPDB).

August 2008  to

December 2012

 

172.76 Lakh

JV of Minconsult, Malaysia

3

Consultancy Services for owner Engineering for Construction of  150 MW Peaking Power Plant  Complex at Khulna, Funded by Asian Development Bank (ADB) Under Bangladesh Power Development Board (BPDB).

January 2012 to

December 2014

172.76 Lakh

Jv of Minconsult, Malaysia

4

Consultancy Services for owner Engineering for Construction of  up- Gradation of  150 MW PPPP     up to 225MW Combined Cycle   Power Plant at Sirajgonj  Under NWPGCL / BPDB.

March 2013 to

December 2016

235.09 Lakh

Jv of Minconsult, Malaysia

5

Consultancy Services for owner Engineering for Construction of  up- Gradation of  150 MW PPPP     up to 225MW Combined Cycle  Power Plant Under NWPGCL / BPDB. Funded by ADB.

April 2015 to September 2017

182.36 Lakh

Jv of Minconsult, Malaysia

6

Consultancy Services for owner Engineering for Construction of 225 MW Combined Cycle Power Plant (2nd unit) at Sirajgonj Under North West Power Gower Co. Ltd. (NWPGCL).

March 2016 to December 2018

 

Jv of Minconsult, Malaysia

7

Consultancy Services for owner Engineering for Construction of 225 MW Combined Cycle Power Plant (3rd unit) at Sirajgonj Under North West Power Gower Co. Ltd. (NWPGCL).

February 2016 to December 2019

 

NOFEAR,UKRAINE

8

Consultancy Services for Construction of Land- Development & Other Infrastructure for 350 MW Coal Power Plant wander Rural Power Co. Ltd. (RPCL)

June 2016 to

June 2018

 

NOFEAR,UKRAINE



Some Power Plants individual projects

-------------------------------------------------------------------------------


Card image cap
Bibiyana – III, 400 MW

GT + GTG + HRSG + ST+ STG, river water intake , WT plant + 400kV Switch yard , 400kV & 230kV EHV underground Cable , Including administrative and housing complex , medical Center with equipment , rest house, officers club, dormitory house. * Open Cycle, Combined Cycle, Gass Turnibe Steam- Turbine, Boiler, Cheminoy, Pile foundation for heavy- Power Plant Equipment, Erection, Testing, Commissioning, Administrative Building, Staff quarter, Dormitory, overhead water Tank. Water Treatment Plant. Internal Road, RCC Jetty on Kushira- River for unloading of heave Power Plant Equipment, Pump, Motor, Pipping work, IT- Work etc. * Design Approval, Procurement Services. * Construction Supervision. * Project Management, Meeting with Client, Monitoring. .

More..
Card image cap
225MW Combined Cycle Power Plant Project

A Simple Cycle 150MW Gas Turbine Power Plant was installed in Sirajganj district, Bangladesh. To increase the generative capacity of this plant, North West Power Generation Company Ltd, (NWPGCL) intends to convert this gas turbine power plant to a 225MW Combined Cycle Power Station.

More..
Card image cap
225MW Combined Cycle PowerPlant (2nd Unit)

Provide Consulting services for Preliminary Design, Engineering, preparation of tender document, bid evaluation, approval of design, drawing, supervision of construction including Land Development, Internal Road etc, installation, testing & commissioning, handing over plant including issuance of Provisional Acceptance Certificate (PAC) of the peaking power plants.

More..
Card image cap
150 MW Peaking PowerPlant

150MW Gas Turbine Generating Unit, 132KV Switchyard (Including Power Evacuation to the Bangladesh National Grid).

Provide Consulting services for Preliminary Design, Engineering, preparation of tender document, bid evaluation, approval of design, drawing, supervision of construction including Land Development, Internal Road etc, installation, testing & commissioning, handing over plant including issuance of Provisional Acceptance Certificate (PAC) of the peaking power plants.